Planning Application: 088770 (Cork County Council )
File Number:
088770
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
05/09/2008
Decision Due Date:
10/12/2008
Validated Date:
05/09/2008
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
08/12/2008
Leave to Appeal:
Appeal Date:
08/01/2009
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
Michael Murnane
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
An increase in hub height from 60 to 85 metres and rotor blade diameter from 66 to 82 metres as well as the addition of 1no. wind turbine to the permitted wind farm development at Cahernafulla. Associated changes to include relocation of permitted turbines, relocation of permitted substation & access tracks, and increase in site area to provide for new access road and entrance
Development Address:
Cahernafulla, Kilberrihert, Aghabullogue
Architect Name:
, Monika Hubczuk-Enerco Energy Ltd
Location Key:
KILBERRIHERT
Electoral Division:
Planner:
Sharon McDonnell
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
No
Comments:
Decision
Decision Date:
08/12/2008
Manager Order:
08/4786
Decision Type:
Conditional
Number of Conditions:
0
Grant Date:
27/03/2009
Grant Managers Order #:
Section 47
Apply?:
F
Part 5
Apply?:
No
Expiry Date:
26/03/2014
Decision Description:
An increase in hub height from 60 to 85 metres and rotor blade diameter from 66 to 82 metres as well as the addition of 1no. wind turbine to the permitted wind farm development at Cahernafulla. Associated changes to include relocation of permitted turbines, relocation of permitted substation & access tracks, and increase in site area to provide for new access road and entrance
Construction of overhead transmission line of single circuit 110kv from approved wind farm substation at Carrigduff to ESB Clashavoon substation at Aughinida
An increase in hub height from 60 to 85 metres and rotor blade diameter from 66 to 82 metres as well as the addition of 1no. wind turbine to the permitted wind farm development, associated changes to turbine layout, underground cabling, onsite tracks and substation
No Environment Impact Assesments Associated with this Application