Planning Application: 156966 (Cork County Council )
File Number:
156966
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
22/12/2015
Decision Due Date:
07/06/2016
Validated Date:
18/01/2016
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
03/06/2016
Leave to Appeal:
Appeal Date:
16/06/2016
Commenced Date:
Submissions By:
16/05/2016
Applicant Details
Applicant name:
Cleanrath Windfarm Ltd
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
The proposed wind farm will comprise the provision of a total of 11 no. wind turbines with a maximum ground to blade tip height of up to 150m, upgrading of existing and provision of new internal access roads, provision of a wind anemometry mast (height up to 100 metres), 2 no. borrow pits, underground electrical cabling, underground grid connection electrical cabling including all associated infrastructure, junction accommodation works for the proposed turbine delivery route and provision of a temporary roadway to facilitate turbine component deliveries, 1 no. electricity sub-station with control building and associated equipment, 1 no. construction compound, upgrading of the existing site access junctions, permanent signage, and all ancillary site works.
The proposed development comprises the redesign of a wind farm at this location previously considered by Cork County Council and An Bord Pleanala under pl. ref: 11/5245, and PL 04.240801 respectively.
The proposed wind farm will comprise the provision of a total of 11 no. wind turbines with a maximum ground to blade tip height of up to 150m, upgrading of existing and provision of new internal access roads, provision of a wind anemometry mast (height up to 100 metres), 2 no. borrow pits, underground electrical cabling, underground grid connection electrical cabling including all associated infrastructure, junction accommodation works for the proposed turbine delivery route and provision of a temporary roadway to facilitate turbine component deliveries, 1 no. electricity sub-station with control building and associated equipment, 1 no. construction compound, upgrading of the existing site access junctions, permanent signage, and all ancillary site works.
The proposed development comprises the redesign of a wind farm at this location previously considered by Cork County Council and An Bord Pleanala under pl. ref: 11/5245, and PL 04.240801 respectively.