Planning Application: 234602 (Cork County Council )
File Number:
234602
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
31/03/2023
Decision Due Date:
12/02/2024
Validated Date:
14/04/2023
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
26/01/2024
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
04/05/2023
Applicant Details
Applicant name:
Irish Distillers Limited
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
The extension and expansion of the existing Midleton Distillery and all associated site development works. The proposed development includes, (A) a 2 storey over basement ‘pot still’ building with ancillary pot still tank farm and mechanical vapour recompression (MVR) building. (B) a 2-9 storey ‘column still’ building with ancillary column still tank farm and cooling tower, (C) a 3-7 storey over partial basement ‘brewhouse’ building with ancillary fermenter structures, (D) a pipe rack structure connecting the proposed pot still, column still and brewhouse buildings with the existing distillery, (E) an internal link bridge crossing the Dungourney River which traverses the site, serving as a vehicular and pedestrian connection between the existing distillery and the proposed distillery extension, (F) demolition of an existing industrial building, removal of existing hardstand areas and culverting of a section of the existing mill race, to facilitate the construction of a biogas plant comprising a series of plant and tank structures, a single storey ammonia removal building and change of use and alterations of existing workshop/warehouse no. 1 and warehouse no. 3 to accommodate associated plant and equipment, (G) other ancillary structures including the construction of a single storey 38kV substation and associated electrical compound, security buildings, staff welfare buildings and car park shelters, (H) all other ancillary site development including the diversion of existing gas and ESB lines which traverse the lands, the upgrade of existing waste water treatment plant at the distillery, attenuation basins, fire water basin, noise attenuation fencing, parking areas, planted boundary berm and signage, (I) access to proposed development will be provided via a new entrance from the Old Youghal Road (R907) to the south. The proposed development will also be accessible from the existing distillery entrances from the Dungourney Road (R627) and Distillery Walk (L-9408) to the north and west of the lands. The proposed development is for modifications to an establishment to which the Major Accident Directives applies and is for the purpose of the activity requiring an integrated pollution control license [Industrial Emissions Directive (IED) licence]. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) have been prepared and will be submitted to the planning authority with the application
Development Address:
Park South, Castleredmond & Park North, Midleton, Co.Cork
Architect Name:
Location Key:
PARK SOUTH
Electoral Division:
Planner:
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
Waste Licence Required:
Protected Structure:
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
No
Comments:
Decision
Decision Date:
26/01/2024
Manager Order:
4120
Decision Type:
Conditional
Number of Conditions:
64
Grant Date:
28/02/2024
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
No
Expiry Date:
Decision Description:
The extension and expansion of the existing Midleton Distillery and all associated site development works. The proposed development includes, (A) a 2 storey over basement ‘pot still’ building with ancillary pot still tank farm and mechanical vapour recompression (MVR) building. (B) a 2-9 storey ‘column still’ building with ancillary column still tank farm and cooling tower, (C) a 3-7 storey over partial basement ‘brewhouse’ building with ancillary fermenter structures, (D) a pipe rack structure connecting the proposed pot still, column still and brewhouse buildings with the existing distillery, (E) an internal link bridge crossing the Dungourney River which traverses the site, serving as a vehicular and pedestrian connection between the existing distillery and the proposed distillery extension, (F) demolition of an existing industrial building, removal of existing hardstand areas and culverting of a section of the existing mill race, to facilitate the construction of a biogas plant comprising a series of plant and tank structures, a single storey ammonia removal building and change of use and alterations of existing workshop/warehouse no. 1 and warehouse no. 3 to accommodate associated plant and equipment, (G) other ancillary structures including the construction of a single storey 38kV substation and associated electrical compound, security buildings, staff welfare buildings and car park shelters, (H) all other ancillary site development including the diversion of existing gas and ESB lines which traverse the lands, the upgrade of existing waste water treatment plant at the distillery, attenuation basins, fire water basin, noise attenuation fencing, parking areas, planted boundary berm and signage, (I) access to proposed development will be provided via a new entrance from the Old Youghal Road (R907) to the south. The proposed development will also be accessible from the existing distillery entrances from the Dungourney Road (R627) and Distillery Walk (L-9408) to the north and west of the lands. The proposed development is for modifications to an establishment to which the Major Accident Directives applies and is for the purpose of the activity requiring an integrated pollution control license [Industrial Emissions Directive (IED) licence]. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) have been prepared and will be submitted to the planning authority with the application