Planning Application: 236182 (Cork County Council )
File Number:
236182
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
27/10/2023
Decision Due Date:
02/04/2024
Validated Date:
08/11/2023
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
02/04/2024
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
30/11/2023
Applicant Details
Applicant name:
Ingredients Solutions Ltd.
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
1) A light industrial building for the use of cheese portioning and packaging, 2) Ancillary office accommodation, 3) Plant and electrical substation rooms, 4) Storm water network to include attenuation, infiltration system and outfall storm line, 5) Foul water network to include a pre-discharge treatment system to the public sewer, pumped sump and rising main, 6) Staff carparking and bike stands, 7) Totem signage, 8) Works associated with a new vehicular and pedestrian entrance from the R577, 9) All associated site works and site services. A Natura Impact Statement will be submitted to the Planning Authority with the application.
Development Address:
Gneeves, Boherbue, Mallow, Co Cork
Architect Name:
Location Key:
GNEEVES (ED BOHERBOY)
Electoral Division:
Planner:
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
Waste Licence Required:
Protected Structure:
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
No
Comments:
Decision
Decision Date:
02/04/2024
Manager Order:
4437
Decision Type:
Conditional
Number of Conditions:
63
Grant Date:
10/05/2024
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
No
Expiry Date:
Decision Description:
1) A light industrial building for the use of cheese portioning and packaging, 2) Ancillary office accommodation, 3) Plant and electrical substation rooms, 4) Storm water network to include attenuation, infiltration system and outfall storm line, 5) Foul water network to include a pre-discharge treatment system to the public sewer, pumped sump and rising main, 6) Staff carparking and bike stands, 7) Totem signage, 8) Works associated with a new vehicular and pedestrian entrance from the R577, 9) All associated site works and site services. A Natura Impact Statement will be submitted to the Planning Authority with the application.