Planning Application: 244606 (Cork County Council )
File Number:
244606
Application Type:
PERMISSION
Planning Status:
DECISION MADE
Received Date:
10/04/2024
Decision Due Date:
18/11/2024
Validated Date:
22/04/2024
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
18/11/2024
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
14/05/2024
Applicant Details
Applicant name:
Dairygold Co-Operative Society Ltd
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
Permission to erect photovoltaic panels on a ground mounted system. The development will comprise of a 5.00 MWp solar PV farm on 6.61 hectares of land located to the south of the existing Dairygold Co-Operative Castlefarm processing facility. The electricity generated will be used by the Dairygold site, which currently operates under an industrial emissions licence reg no. P0404-02. The development will comprise of photovoltaic panels with ground mounted frames together with all ancillary cabling and electrical infrastructure; 1 no. transformer cabin; using all temporary ways and temporary construction compound/ set-down area included on the application.
Development Address:
Dairygold Co-Operative Society Ltd., Castle Park, Mitchelstown, Co. Cork
Architect Name:
Location Key:
MITCHELSTOWN (ED MITCHELSTOWN)
Electoral Division:
Planner:
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
Waste Licence Required:
Protected Structure:
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
No
Comments:
Decision
Decision Date:
18/11/2024
Manager Order:
5558
Decision Type:
Conditional
Number of Conditions:
16
Grant Date:
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
No
Expiry Date:
Decision Description:
Permission to erect photovoltaic panels on a ground mounted system. The development will comprise of a 5.00 MWp solar PV farm on 6.61 hectares of land located to the south of the existing Dairygold Co-Operative Castlefarm processing facility. The electricity generated will be used by the Dairygold site, which currently operates under an industrial emissions licence reg no. P0404-02. The development will comprise of photovoltaic panels with ground mounted frames together with all ancillary cabling and electrical infrastructure; 1 no. transformer cabin; using all temporary ways and temporary construction compound/ set-down area included on the application.