Planning application details ref: 255034 Cork County Council

100%100% Complete (warning)

Planning Application: 255034 (Cork County Council )
File Number: 255034
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 30/05/2025 Decision Due Date: 24/07/2025
Validated Date: 11/06/2025 Invalidated Date:
Further Info Requested: Further Info Received:
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 24/07/2025
Leave to Appeal: Appeal Date:
Commenced Date: Submissions By: 03/07/2025

Applicant Details

Applicant name: Stream BioEnergy Ireland Limited
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: Permission for the proposed development will consist of the completion of the Renewable Biogas Plant as permitted by extant planning permission ref. 15/4926, extended by ref 20/5549 and amended by ref 23/5586. All demolition, site clearance, earthworks and formation for foundations will be complete under the current permission. The proposed plant will generate renewable biogas from 90,000 tonnes of non-hazardous biodegradable waste (‘Brown bin’ domestic and commercial waste) per annum utilising anaerobic digestion (AD) technology. It is proposed to upgrade the biogas to biomethane and inject it into the adjacent gas grid to replace fossil fuel derived natural gas. Other products from the process include digestate (a nutrient rich biofertilizer) as well as biogenic (natural) carbon dioxide. The proposed development will consist of the construction of: 1) main process building (c.3,762m2 gross floor area (GFA), max 14.5m high) incorporating feedstock reception and processing area, digestate treatment areas, dewatering and storage areas, quarantine areas, an odour control system and associated 25m high stack with signage on the south elevation. 2)Tank farm (c. 3,183m3 footprint, 4m high bund wall) encompassing a total of 6 tanks including four digestor tanks (20.15m max. height, c.3,400m3 capacity) a digestate storage tank (20.15m max. height, c.3,400m3 capacity), a suspension buffer tank ( 10.5m max.height, c.700m3 capacity (, an containerised desulphurisation plant and associated 2 tanks (14m max height, c120m3 capacity), 2 no. enclosed pump rooms (room no.1 -53.58m2 GFA and room no.2 – 23.69m2 GFA), and enclosed feedstock pump room (53.58m2 GFA and 3.6m high), 3 sediment settlement tanks (c.5.84(L), c.2.23m (W) & c.3.78(H) on a raised platform at 6m above ground level, stairwells, pumps, gantry walkways, 2 bund access stairs and tank emergency access ladders; 3) A biogas upgrade plant and gas entry unit; 1 no. containerised Combined Heat and Power (CHP) 1.5MW unit with an associated 28m high stack, a carbon dioxide liquefaction plant, a biogas holder (10.56 max. height, c.2,000m3) with 4 no. c.13.12m high lightning rods, a 9.26m gas flare, a containerised boiler with 10m stack, a transformer station, a propane storage tank, an emergency generator, 2 no. weighbridges, weighbridge office (c.17.2m2 GFA and 4.55m high), a fire water tank (c.1,000m3 and 14.12m high), a bunded vehicle refuelling area with a fuel storage tank (2.5m3) and a wheel wash, 4) Adminis
Development Address: Inchera, Little Island, Co.Cork
Architect Name: Location Key: INCHERA
Electoral Division: Planner:
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: Waste Licence Required:
Protected Structure: Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: No Comments:

Decision

Decision Date: 24/07/2025 Manager Order: 5024
Decision Type: Conditional Number of Conditions: 32
Grant Date: 29/08/2025 Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?: No
Expiry Date:
Decision Description: Permission for the proposed development will consist of the completion of the Renewable Biogas Plant as permitted by extant planning permission ref. 15/4926, extended by ref 20/5549 and amended by ref 23/5586. All demolition, site clearance, earthworks and formation for foundations will be complete under the current permission. The proposed plant will generate renewable biogas from 90,000 tonnes of non-hazardous biodegradable waste (‘Brown bin’ domestic and commercial waste) per annum utilising anaerobic digestion (AD) technology. It is proposed to upgrade the biogas to biomethane and inject it into the adjacent gas grid to replace fossil fuel derived natural gas. Other products from the process include digestate (a nutrient rich biofertilizer) as well as biogenic (natural) carbon dioxide. The proposed development will consist of the construction of: 1) main process building (c.3,762m2 gross floor area (GFA), max 14.5m high) incorporating feedstock reception and processing area, digestate treatment areas, dewatering and storage areas, quarantine areas, an odour control system and associated 25m high stack with signage on the south elevation. 2)Tank farm (c. 3,183m3 footprint, 4m high bund wall) encompassing a total of 6 tanks including four digestor tanks (20.15m max. height, c.3,400m3 capacity) a digestate storage tank (20.15m max. height, c.3,400m3 capacity), a suspension buffer tank ( 10.5m max.height, c.700m3 capacity (, an containerised desulphurisation plant and associated 2 tanks (14m max height, c120m3 capacity), 2 no. enclosed pump rooms (room no.1 -53.58m2 GFA and room no.2 – 23.69m2 GFA), and enclosed feedstock pump room (53.58m2 GFA and 3.6m high), 3 sediment settlement tanks (c.5.84(L), c.2.23m (W) & c.3.78(H) on a raised platform at 6m above ground level, stairwells, pumps, gantry walkways, 2 bund access stairs and tank emergency access ladders; 3) A biogas upgrade plant and gas entry unit; 1 no. containerised Combined Heat and Power (CHP) 1.5MW unit with an associated 28m high stack, a carbon dioxide liquefaction plant, a biogas holder (10.56 max. height, c.2,000m3) with 4 no. c.13.12m high lightning rods, a 9.26m gas flare, a containerised boiler with 10m stack, a transformer station, a propane storage tank, an emergency generator, 2 no. weighbridges, weighbridge office (c.17.2m2 GFA and 4.55m high), a fire water tank (c.1,000m3 and 14.12m high), a bunded vehicle refuelling area with a fuel storage tank (2.5m3) and a wheel wash, 4) Adminis

Appeal Details


Appeal Details
Notification Date: BP Reference #:
Appeal Type: File Forward Date:
Submission Due Date: Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: