Planning Application: 254066 (Cork County Council )
File Number:
254066
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
22/01/2025
Decision Due Date:
18/03/2025
Validated Date:
29/01/2025
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
14/03/2025
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
25/02/2025
Applicant Details
Applicant name:
Circle K Ireland Energy Limited
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
Permission for A high-power electric vehicle charging hub and associated infrastructure consisting of the following: 1) installation of 10 no. electric vehicle charging with 5 no. associated charging units to replace 12 no. existing car parking spaces, 2) installation of a new canopy above EV charging spaces with internally illuminated signage, 3) new EV banner sign, 4) relocation of existing lighting columns and electrical cabinet, 5) installation of a new ESB substation and 6) all other associated site development, landscaping, road tie in and surface water drainage works
Development Address:
Circle K, Junction 14, M8, Gortore, Fermoy, Co.Cork
Architect Name:
Location Key:
GORTORE
Electoral Division:
Planner:
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
Waste Licence Required:
Protected Structure:
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
No
Comments:
Decision
Decision Date:
14/03/2025
Manager Order:
4343
Decision Type:
Conditional
Number of Conditions:
15
Grant Date:
29/04/2025
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
No
Expiry Date:
Decision Description:
Permission for A high-power electric vehicle charging hub and associated infrastructure consisting of the following: 1) installation of 10 no. electric vehicle charging with 5 no. associated charging units to replace 12 no. existing car parking spaces, 2) installation of a new canopy above EV charging spaces with internally illuminated signage, 3) new EV banner sign, 4) relocation of existing lighting columns and electrical cabinet, 5) installation of a new ESB substation and 6) all other associated site development, landscaping, road tie in and surface water drainage works