Application Type:
EXTENSION OF DURATION
Planning Status:
APPLICATION FINALISED
Received Date:
24/02/2009
Decision Due Date:
20/04/2009
Validated Date:
24/02/2009
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Decision Date:
06/04/2009
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
Carraigcannon Wind Farm Ltd.
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
Completion of windfarm to include 10 no. wind turbines, ESB control building, compound and ancillary site works permitted under Pl. Reg. No. 03/4181 (New pemisssion to expire on 27/02/2012)
Development Address:
Carragraigue, Charlesfield, Rathcoole, Mallow
Architect Name:
Location Key:
CARRAGRAIGUE
Electoral Division:
Planner:
Dave Ryan
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
No
Comments:
Decision
Decision Date:
06/04/2009
Manager Order:
05/09
Decision Type:
Number of Conditions:
0
Grant Date:
Grant Managers Order #:
Section 47
Apply?:
F
Part 5
Apply?:
No
Expiry Date:
Decision Description:
Completion of windfarm to include 10 no. wind turbines, ESB control building, compound and ancillary site works permitted under Pl. Reg. No. 03/4181
Completion of wind farm consisting of 19 no. wind turbines of 80m hub height and 80m blade diameter and electrical substation with control building granted under Planning Reg. No. 01/1248
Erection of new 38kV line from an 110kV station at the wind farm in Boggeragh to the ESB station at Carrigcannon wind farm. The proposed line will consist of 3no. conductors at 2 metres apart supported on double wood poles & approx. 150m apart. Angle structures will consist of lattice steel towers. Total length of the tower is approx 3.5kms passing through the townlands of Inchamay North, Crinnaloo South & Carrigcannon
construction of substation building measuring approximately 16m X 6m, a fenced electrical plant area measuring approximately 29m X 18m, car parking and incidental site works