Planning Application: 095188 (Cork County Council )
File Number:
095188
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
15/04/2009
Decision Due Date:
09/06/2009
Validated Date:
15/04/2009
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
09/06/2009
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
The Electricity Supply Board
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
Erection of new 38kV line from an 110kV station at the wind farm in Boggeragh to the ESB station at Carrigcannon wind farm. The proposed line will consist of 3no. conductors at 2 metres apart supported on double wood poles & approx. 150m apart. Angle structures will consist of lattice steel towers. Total length of the tower is approx 3.5kms passing through the townlands of Inchamay North, Crinnaloo South & Carrigcannon
Development Address:
Inchamay North, Crinnaloo South & Carrigcannon
Architect Name:
, Sean McCarthy
Location Key:
INCHAMAY NORTH
Electoral Division:
Planner:
Catriona Cregan
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
No
Comments:
Decision
Decision Date:
09/06/2009
Manager Order:
09/1369
Decision Type:
Conditional
Number of Conditions:
0
Grant Date:
10/07/2009
Grant Managers Order #:
Section 47
Apply?:
F
Part 5
Apply?:
No
Expiry Date:
09/07/2014
Decision Description:
Erection of new 38kV line from an 110kV station at the wind farm in Boggeragh to the ESB station at Carrigcannon wind farm. The proposed line will consist of 3no. conductors at 2 metres apart supported on double wood poles & approx. 150m apart. Angle structures will consist of lattice steel towers. Total length of the tower is approx 3.5kms passing through the townlands of Inchamay North, Crinnaloo South & Carrigcannon
Completion of wind farm consisting of 19 no. wind turbines of 80m hub height and 80m blade diameter and electrical substation with control building granted under Planning Reg. No. 01/1248
Completion of windfarm to include 10 no. wind turbines, ESB control building, compound and ancillary site works permitted under Pl. Reg. No. 03/4181 (New pemisssion to expire on 27/02/2012)
New 38kV line from a 110kV station at the wind farm in Boggeragh to an ESB station at Carrigcannon wind farm. The proposed line will consist of 3no. conductors at 2 metres apart supported on double wood poles & approx 150 metres apart. Angle structures will consist of lattice steel towers. Total length of the line is approx 3.5kms passing through the townlands of Inchamay North, Crinnaloo South & Carrigcannon
1no. wind turbine of 80m hub height & 90m rotor diameter, widening of existing access track, construction of turbine hardstanding area, underground cabling & associated site works
No Environment Impact Assesments Associated with this Application