Planning Application: 065398 (Cork County Council )
File Number:
065398
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
09/03/2006
Decision Due Date:
15/05/2007
Validated Date:
09/03/2006
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
26/04/2007
Leave to Appeal:
Appeal Date:
23/05/2007
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
Healy Brothers Ltd
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
Construction of timber frame manufacturing factory consisting of single storey manufacturing/dispatch area, single storey store area, two storey office, external lean-to canopies, signage, detached plant room building, site entrance, internal roadways, provision for car parking, waste water treatment plant and associated site works
Development Address:
Ballynabointra, Midleton
Architect Name:
, Murphy McCarthy
Location Key:
BALLYNABOINTRA
Electoral Division:
Planner:
Aileen Hurley
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
No
Comments:
Decision
Decision Date:
26/04/2007
Manager Order:
07/2469
Decision Type:
Conditional
Number of Conditions:
0
Grant Date:
Grant Managers Order #:
Section 47
Apply?:
F
Part 5
Apply?:
No
Expiry Date:
Decision Description:
Construction of timber frame manufacturing factory consisting of single storey manufacturing/dispatch area, single storey store area, two storey office, external lean-to canopies, signage, detached plant room building, site entrance, internal roadways, provision for car parking, waste water treatment plant and associated site works
Site development works to facilitate the future construction of biotechnology manufacturing facility to include temporary construction access with associated widening of road, signalised junction at intersection off N25 and Hedgy Boreen with associated road works, 20kV substation in a compound with switchgear building and 2 no. transformer pads, gas compound/above ground installation with associated conrtol buildings, earthworks to include cut and fill operations to prepare the site for construction of future buildings, attenuation/retention pond, demolition of 2 no. dwellinghouses, internal access roads, provision for 600 no. surface level car parking spaces, gravelled areas for future buildings, retaining wall and lighting standards, underground services and associated manholes, site boundary treatments to include security fencing and landscaping and all associated and ancillary site development works.
Retention and completion of vehicle maintenance facility incorporating two storey office over storage area, installation of proprietary treatment unit and associated site works
No Environment Impact Assesments Associated with this Application